Mill Creek Canyon Road could be widened starting next spring in two-year project

Mill Creek Canyon road could be widened from the winter gate parking area all the way up to the Upper Big Water Trailhead, according to a proposal by the Federal Highway Administration, Salt Lake County, Millcreek and other federal agencies.An enviro


  • Apr 03 2024
  • 0
  • 1 Views
Mill Creek Canyon Road could be widened starting next spring in two-year project
Mill Creek Canyon Road could be widened starting next spring in two-year project

Mill Creek Canyon road could be widened from the winter gate parking area all the way up to the Upper Big Water Trailhead, according to a proposal by the Federal Highway Administration, Salt Lake County, Millcreek and other federal agencies.

An environmental assessment released in early March states that spring, summer, and fall access to the upper canyon “would be limited or restricted for the 2-year construction period.” Construction would start in May 2025.

(Federal Highway Administration) A map from the environmental assessment shows where trails would be closed to public access if the proposal to widen parts of Mill Creek Canyon Road move forward.
(Federal Highway Administration) A map from the environmental assessment shows where trails would be closed to public access if the proposal to widen parts of Mill Creek Canyon Road move forward.

“We know that this canyon is loved by so many and really what this is about is preparing for the future,” Salt Lake County Mayor Jenny Wilson said in 2021 when the project was first announced.

Salt Lake District Bekee Hotze of the Forest Service also voiced support for the project in 2021. “Access to Mill Creek Canyon and the facilities within the canyon are deteriorating and not keeping up with the use that’s currently going on,” Hotze said. “Where feasible, the road will be widened to accommodate the multiuse that we are currently seeing in the canyon.”

The upper canyon would be accessible during the winter between Dec. 15 through March 15.

Other changes under the proposal:

• A roundabout would be built about 250 feet east of the winter gate parking area to “provide snowplows and large vehicles with a convenient place to turn around.”

• The winter gate would be moved 200 feet East.

• The 1.5-mile strip from the proposed new roundabout to Elbow Fork would be widened to 24 feet (the strip currently varies from 16 to 24 feet). It would create 10-foot-wide lanes and a 4-foot-wide bicycle lane on the uphill side.

• More formal parking areas would be created and “informal” ones removed. The report estimates that the total parking capacity will remain about the same through these changes.

• The Upper Big Water Trailhead parking area would be expanded from .36 acres to .84.

• Crosswalks and signs would be installed in areas where people frequently cross to access trails.

(Federal Highway Administration) A rendering of a proposed retaining wall on Mill Creek Canyon road.
(Federal Highway Administration) A rendering of a proposed retaining wall on Mill Creek Canyon road.

What are the impacts?

Trees would need to be removed in some areas, and the loss of streamside vegetation to replace culverts “could have other effects to water quality and aquatic species,” according to the environmental assessment.

There are three small wetlands within the proposed project area that could be impacted as well.

Plus (aside from the winter) hikers, bikers and those with dogs would no longer have access to the upper canyon during the project.

“Users travelling farther distances to reach Mill Creek Canyon could more easily choose alternate destinations with little to no adverse impact,” the EIS states. It lists City Creek Canyon as one alternative, although canyon access is limited through 2027 due to construction at the water treatment plant.

Save Our Canyons wrote on Instagram: “We believe that safety goals can be better achieved by reducing the number of personal cars in the canyon, rather than treating pavement as the solution.”

The public can still comment

The full proposal can be found here and a story map outlining the changes to Upper Mill Creek Canyon here. The public has until April 5 to review the proposal and comment.

(Federal Highway Administration) A map from the environmental assessment shows proposed changes to Mill Creek Canyon Road.
(Federal Highway Administration) A map from the environmental assessment shows proposed changes to Mill Creek Canyon Road.

This is a developing story check back for updates.